Sattva Songbird's Completion Date is 6 May 2029 (5 years from the initial launch), which marks the change of the property to an operational asset from a blueprint. The completion date is clearly stated in contracts, and builders carefully plan to make it ready for use and living.
A completion date is when the construction of a project is expected to be over. It marks the finish of the project, and builders usually aim to hand over the project on the specified dates on time.
The Sattva Songbird construction process is divided into schedules so that it can be finished on time on the specified dates as follows,
Project Work | Estimated From Date | Estimated To Date |
Earthwork and other leveling work | 01-06-2024 | 27-06-2025 |
Foundation footing work | 02-08-2024 | 25-09-2025 |
Upto Plinth Level | 02-08-2024 | 25-09-2025 |
Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 16-02-2025 | 01-03-2026 |
Retaining wall (All types) | 02-08-2024 | 27-02-2026 |
Project Work | Estimated From Date | Estimated To Date |
RCC or MS Framed structure | 04-12-2024 | 01-03-2026 |
Masonry Work | 01-03-2025 | 06-02-2027 |
Plastering inside, outside & Ceiling | 31-03-2025 | 02-11-2027 |
Joinery: Doors, Windows, Ventilators etc | 31-03-2025 | 08-04-2029 |
Basic work of Water supply, Sanitary and Electrical work | 27-08-2024 | 02-11-2027 |
Dadoing, Skirting, Flooring, Tiles work (All types) | 30-05-2027 | 10-12-2028 |
Railing and Grill fixing | 01-03-2025 | 10-12-2028 |
Project Work | Estimated From Date | Estimated To Date |
Electrical work, Water supply, and Sanitary Finishing | 30-05-2027 | 08-02-2029 |
Painting | 29-06-2027 | 08-02-2029 |
Fire prevention and firefighting fitting and fixture with network | 17-04-2025 | 08-04-2029 |
Weather Proof work (tile, concrete) | 01-01-2027 | 22-04-2027 |
Wardrobe, Showcase, Kitchen cabinet, Puja work | ||
Elevation work | 28-06-2025 | 08-02-2029 |
Internal and External work as per sanctioned drawings | 30-09-2025 | 06-05-2029 |
The project will be closely monitored to make sure that it clearly follows the schedules and to finished it exactly on time. After the project is fully finished, it will be checked, and a completion certificate will be issued. After that, buyers can start taking possession of their properties.
As Sattva Songbird is a RERA approved project, it will be completed on time on the given completion dates. As Sattva Group is known for finishing their projects on time, Sattva Songbird will also be completed on time, and buyers can take ownership of the houses on the exact given dates in 2029.